GDh. Rathafandhoo Powerhouse: The new powerhouse is 60% complete, with roofing currently underway. This project, managed by a private contractor, is set to improve electricity service quality and capacity for both residents and businesses on the island.
HDh. Nolhivaran Office Building: The new office building is 70% finished, with tasks like door installation, tiling, and painting remaining. Designed for both technical and administrative staff, this modern facility will provide improved access to services and is expected to be completed by the end of November.
L. Fonadhoo Powerhouse Expansion: This project has reached 92% completion, focusing on increasing power capacity with space for two additional 1.2-megawatt gensets. Major works, including roofing and flooring, are done, and final tasks are expected to wrap up within two weeks.
B. Kendhoo Powerhouse and Office Building: Construction is 75% complete, with door installation and main tank work ongoing. This project aims to enhance electricity services and is also targeted for completion by the end of November.
M. Muli Office Building: Currently at 79% completion, this two-story building will include modern safety features and improved facilities for staff and customers. Final tasks, including electrical wiring and plumbing, are in progress, with completion expected by the end of November.
Overall, Fenaka's ongoing projects are poised to significantly improve electrical capacity and service quality, alongside enhancing workplace environments for staff.